PM Central R2.0 Use Case Series: How to Update Progress

Project managers have to monitor a project’s progress throughout its entire life cycle. They need to be able to track the actual dates, actual duration and actual cost for the project, in addition to the planned dates and planned cost.

One of the new features available in SharePoint Project Management Central™ R2.0 is the ability to update a project’s progress in order to make sure that it is on track—providing maximum project-management capability.

Updating a Project’s Progress

Before you update your project’s progress, make sure to enter the Budget Cost and Budget Work for the project. Follow steps 1-3 in this blog post to learn how.

At the project site, go to the Tasks > Progress Management tab.

The Progress Management tab has two Web Parts that allow you to update progress: the Update Task Progress Web Part and the Update Project Cost & Schedule Web Part.

Update Task Progress
Use this Web Part to get the Actual Start Date and Actual Due Date for the project tasks. Use this Web Part after you capture the baseline, not before.

To update task progress:

  • Create tasks and allocate resources to the tasks. Make sure that task information is updated and recalculated in the All Tasks tab before updating the progress.
  • Click Update Progress Information.

  • The Actual Start Date and Actual Due Date will update as follows:
    • Actual Start Date and Actual Due Date will be updated based on the Start Date and the Due Date if the % Complete is equal to 100.
    • Actual Start Date will be updated using the Start Date only if the % Complete is greater than 0 because that means that the task has started and is in progress.
    • Actual Start Date and Actual Due Date will not be updated if the % Complete is equal to 0 because that means that the task has not started.

Update Project Cost & Schedule
Use this Web Part to view the project’s Actual Duration, Actual Cost and Actual Work. Update the project cost and schedule before you baseline to get the Project Cost and Project Work. After the tasks are started and you have the tasks’ Actual Cost and Actual Work, update the project cost and schedule again to get the Project Actual Duration, Project Actual Cost and Project Actual Work.

To update project cost and schedule:

  • Update the project’s Budget Cost and Budget Work. Follow steps 1-3 in this blog post to learn how.
  • Make sure that the tasks are updated clicking Recalculate in the All Tasks tab.
  • Click Update Project Cost & Schedule.

  • The fields for Project Actual Duration, Project Actual Cost and Project Actual Work are now populated.

Read other blog posts in the PM Central R2.0 use case series, and keep checking the Bamboo Team Blog for more use cases, such as how to set the baseline.

The PM Central team wants to make PM Central the best project management and collaboration tool available for SharePoint. We’re interested in your feedback, and we welcome your comments or questions in the PM Central forum.

Interested in PM Central R2.0? Get a free 30-day trial, or sign up for a free webinar.


    SharePoint

    Applications

    SharePoint apps are stand-alone applications that perform specific tasks on a SharePoint site. Apps can perform functions such as managing a discussion board or knowledge base, performing project management or time tracking tasks, or doing other workflow operations.

    SharePoint

    Product Suites

    Experience greater power and savings by bundling our SharePoint apps and web parts.


    Essentials


    Essentials Plus


    Bamboo Premier


    Project Management Suite


    Knowledge Management Suite


    External User Manager


    SharePoint

    Web Parts

    Extend SharePoint beyond its out-of-the-box capabilities by tailoring it to your requirements with Bamboo Solution’s growing portfolio of Web Parts. Web Parts are the building blocks of pages on a SharePoint site that can be used to customize the user interface and content of a site page. 

    SharePoint

    Product Suites

    Experience greater power and savings by bundling our SharePoint apps and web parts.


    Essentials


    Essentials Plus


    Bamboo Premier


    Project Management Suite


    Knowledge Management Suite


    External User Manager


    Office 365

    Cloud Parts

    Cloud Parts are functional components that extend your SharePoint environment whether it’s hosted, on-premises, or part of Microsoft Office 365. More than mere ports of existing software to the cloud, our Cloud Parts have been built from the ground up to take advantage of the best that the cloud has to offer.

    SharePoint

    Product Suites

    Experience greater power and savings by bundling our SharePoint apps and web parts.


    Cloud Parts Suite for O365/SP Onl.


    Featured Services

    SharePoint Health Check

    A SharePoint Health Check will identify the causes of issues and risks associated with your specific environment, and is custom tailored to provide you with the best recommendations to optimize your SharePoint environment.

    SQL Health Check

    Document recommendations relating to performance, stability, availability, or a specific focus you request of your SQL Server database instances.

    My SharePointXperts

    The truth is that each SharePoint skill may not be a full time job for many organizations, and it is nearly impossible for one person to do everything you need – so augment your team with SharePointXperts; providing the skill sets you need when you need them!